About this project
In project WWTP laundry Klaratex the HydRO WWTP concept is used, combining MBR and RO, to achieve over 75 % recovery of process water within 24 hours. This compact design puts two 20 feet container units on top of concrete tanks which is a great solution for companies with limited available space for waste water treatment.
Specifications
Company | Klaratex |
Year | 2017 |
System | HydRO MBR – RO |
Capacity | 70 m³/d |
Recovery | >75% |
Main contractor | Geo-Engineering NV |
Learn more about exploitation
Full exploitation of any water treatment installation is performed by our specialised team in both process control and technical maintenance. We offer you maximum services with our remote controled systems and on site interventions 7/7d and 24/24h. We can also deliver various kinds of chemicals needed in the treatment process.